A supply agreement with a Chinese manufacturer should connect the commercial framework to each purchase order and to the evidence created during performance. It should identify the exact supplier, establish which document controls, define the goods and specifications, and allocate delivery, inspection, acceptance, payment, warranty and failure risks.
The agreement is different from a distribution agreement: it governs procurement of goods rather than appointment of a reseller. It may also be narrower than a full OEM package where the buyer supplies sensitive designs, owns tooling or controls a manufacturing process. Those matters should be added when the operating model requires them rather than assumed from the word “supply.”
Direct answer
Use a master supply agreement for recurring legal and operational terms, then issue purchase orders containing the commercial details for each release. The documents should state how orders become binding and which terms prevail if a quotation, acknowledgment, invoice or platform record conflicts with the master.
China’s Civil Code supplies rules on sales, performance, risk, inspection, breach, force majeure and termination. The Supreme People’s Court interpretation on the Contract Book addresses issues of formation, validity, interpretation and remedies. Contract drafting should still answer the operational questions directly; relying on default rules after a dispute is slower and less predictable than recording the intended allocation.
Contract hierarchy and order formation
List every document that may form part of the deal: master agreement, specifications, purchase order, supplier acknowledgment, quality manual, approved sample and change order. Establish a precedence clause and prevent boilerplate on invoices or acknowledgments from silently changing the bargain.
State whether a purchase order is accepted by signature, electronic confirmation, shipment or failure to reject within a defined period. Identify authorized ordering channels and personnel. If affiliates may order, clarify whether each affiliate contracts separately and whether any parent guarantee or cross-default applies.
Forecasts, capacity and minimum purchases
Separate planning forecasts from binding orders. Define forecast frequency, firm and flexible windows, capacity reservations, lead times and permitted variation. If the buyer promises a minimum, state how rejected goods, supplier delay, discontinuation and force majeure affect it.
Price-adjustment clauses should identify the trigger, evidence, notice period, calculation and buyer options. A clause that merely permits adjustment for “market conditions” invites argument. Address currency, taxes, freight, tooling or packaging charges and the duration of quoted prices.
Goods, specifications and changes
Identify the goods by product code and controlled specification. Incorporate drawings, materials, tolerances, packaging, labelling, certification and testing where relevant. If an approved sample is used, label and retain it and explain its relationship to written measurements.
No material, component, process, site or subcontractor change should occur outside the agreed change procedure. Require written approval, validation and treatment of affected stock. Version control should make it possible to prove which specification governed a particular batch.
Delivery and the Incoterms boundary
State the delivery date or window, named place, shipping documents, partial-shipment rules and consequences of delay. If using Incoterms, identify the rule, named place and edition. Incoterms can allocate defined delivery tasks, costs and risk, but do not automatically determine title, price adjustment, payment, governing law, tax treatment or quality acceptance.
Deal with early delivery, storage, expedited freight and shortages. If time is critical, define the commercial reason and a proportionate remedy rather than relying only on a general “time is of the essence” phrase.
Inspection and acceptance
Describe pre-shipment, receiving and laboratory inspection, sampling rules and access to records. Set practical notice periods for visible defects and preserve rights for latent defects that could not reasonably be detected earlier.
Acceptance should not be inferred too broadly from payment, use or resale. State what acceptance does and does not waive. Remedies may include sorting, repair, replacement, refund, price reduction and recovery of agreed inspection or transport costs. The buyer should retain samples, photographs, test reports and timely notices.
Title and risk
Specify when title transfers and separately state when risk of loss transfers. Address rejected goods, consignment stock, goods stored at the supplier and buyer-owned materials. An ownership clause may need to be tested against possession, third-party rights and insolvency rules; do not assume it creates effective security.
Invoices and payment
Connect payment to the required invoice, delivery documents and any inspection milestone. State currency, banking charges, tax documentation, credit period, disputed-invoice process and late-payment consequences. Verify beneficiary accounts and require independent confirmation of any change to bank details.
If the buyer needs set-off, retention, holdback or security, draft it expressly and assess enforceability. Avoid giving operational personnel a unilateral power that conflicts with internal approval controls.
Warranties and product compliance
Warranties should cover conformity with specification, workmanship, materials, title, authority and applicable product requirements as relevant. Define the warranty period and the start date, repair or replacement timing, repeat-failure treatment and survival after termination.
Allocate certification, testing, technical-file, traceability, reporting and recall tasks for the relevant markets. Destination-market compliance cannot safely be reduced to a statement that goods are “export quality.”
Shortages, delay and breach
Create an escalation ladder for shortage, missed milestones, repeated quality failure and non-payment. Remedies can include cover purchase, expedited freight, replacement, suspension and termination, subject to the agreed liability regime and applicable law.
Liquidated damages or agreed damages should be drafted around a real commercial risk and reviewed for possible judicial adjustment. A penalty label does not guarantee recovery, and an exclusive-remedy clause may unintentionally remove a remedy the buyer expected to retain.
Force majeure and change of circumstances
Define notice, evidence, mitigation, allocation and long-stop termination. Force majeure should not excuse obligations unaffected by the event or amounts already due. Supply interruption may also result from allocation decisions, subcontractor failure or price pressure that do not automatically qualify.
The Civil Code separately recognizes a change-of-circumstances framework in defined conditions. Parties should not collapse that doctrine into force majeure. A negotiation clause can establish a process, but transaction-specific advice is needed before treating performance as suspended or the contract as adjusted.
Termination and transition
Address termination for uncured material breach, chronic delay, repeated non-conformity, unauthorized changes, insolvency indicators and legal or compliance risk. Specify effects on accepted purchase orders, deposits, finished goods, work in progress, buyer materials, records and continuing warranties.
For an important supplier, include transition supply, tooling or document return where relevant, and cooperation with an alternate source. The buyer should maintain enough current specification and supplier information to make that obligation usable.
Dispute clause and evidence file
Choose governing law, court or arbitration forum, language, service and interim-relief strategy as one package. Confirm the correct Chinese legal name of the supplier and the assets or operations against which relief may be sought.
Maintain the executed master, authority and chop evidence, every purchase order and acknowledgment, specification versions, inspection material, delivery records, invoices, payments, notices and key communications. Export important platform or messaging records with identifying and timing information; screenshots alone may omit context needed to authenticate them.
Supply-agreement checklist
- Confirm the supplier’s registered identity and production role.
- Establish document precedence and order-acceptance mechanics.
- Separate forecasts, capacity reservations and binding orders.
- Control specifications, approved samples and changes.
- Define delivery, Incoterms usage, shortage and delay rules.
- Separate inspection, acceptance and latent-defect rights.
- State title and risk transfer independently.
- Link invoices and payment to documentary milestones.
- Define warranties, remedies and product-compliance ownership.
- Draft force-majeure and change procedures separately.
- Plan termination, open orders and transition support.
- Choose the dispute route and preserve the evidence chain.
Sources
- Civil Code of the PRC, National People’s Congress; effective 1 January 2021.
- SPC Interpretation on the General Principles of the Contract Book of the Civil Code, Supreme People’s Court; effective 5 December 2023.
General legal information only; not legal advice for a specific supply chain, product, contract or dispute.


